PWD Water Main Replacement project update: Construction starting in Center City West

19 Dec 2023 4:38 PM | Travis Oliver (Administrator)

As of mid-December, work to replace the water main along S 22nd is about 75% complete and is estimated to be complete by mid-January 2024. The sewer work will begin immediately after, and is scheduled to take 5 weeks to complete. Re-paving will follow the sewer work. With no unanticipated delays, the project will be complete by late February 2024.